Summary

Upgrading and modifying an existing plant implies organizational constraints, taking into account and adapting to the existing environment. The aim is to remove air-handling units and to build a new plant elsewhere in order to make some space available in order to build a clean room where the air-handling units used to be, without stopping production.

Details

  • Original title: Revamping d'une salle blanche et du traitement de l'air dans un laboratoire.
  • Record ID : 2002-3183
  • Languages: French
  • Source: Chaud Froid Plomb. - n. 646
  • Publication date: 2002/05
  • Document available for consultation in the library of the IIR headquarters only.

Links


See other articles in this issue (4)
See the source